Model Status
Design (Federated) Model
What the model can be relied upon for
A dimensionally correct and coordinated model that can be used to verify compliance with regulatory requirements.The model can be used as the start point for the incorporation of specialist contractor design models and can include information that can be used for fabrication, co-ordination, sequencing and estimating purposes, including the agreement of a target price / guaranteed maximum price.
Output
Integrated production information
Parametric information
Production information for the project: Specific systems, objects and assemblies accurate in terms of specification, size, form, function and location Critical interfaces flagged Fixing methodology Confirmed clash free detailed production programme sequence. Updated: energy use and embodied and in use carbon, detailed design and construction programme
Project costs
Contract Sum/ Target Price/ Agreed Maximum Price Pre-construction whole life cost plan